Legal Risks in Overseas Projects: Insights from the CITIC Tai Fook Western Australia Iron Ore Project
Release time:
2016-06-29
Source:
In the CITIC Pacific West Australia iron ore project, both CITIC Pacific, as the owner, and China Metallurgical Group, as the contractor, have suffered painful lessons. Yet, apart from briefly attracting widespread media attention, this project does not seem to have drawn much attention from legal professionals. This article... From the perspective of the project owner, this brief analysis highlights the insights that this project offers to Chinese enterprises—whether investors or contractors—who are seeking to expand into the global market, particularly in developed countries, from the standpoint of legal risk prevention.
2006 April of the year CITIC Pacific signed an agreement with Mineralogy (whose actual controller is Australian billionaire Clive Palmer). Acquired full equity interests in Sino-Iron and Balmoral Iron, two companies in Western Australia that each hold mining rights to 1 billion tons of magnetite resources, for US$415 million. According to the agreement, if the aforementioned mining area is confirmed to have sufficient resources, CITIC Pacific... It also holds an option to acquire the mining rights for an additional 4 billion tons of magnetite ore. CITIC Pacific stated that if the entire resource base (6 billion tons) were exploited, the project’s annual production capacity could reach 72 million tons. At the time, CITIC Pacific estimated that capital expenditures for the two magnetite projects would amount to approximately US$2.5 billion and that the projects would begin production in 2009.
However, since then, the project has encountered numerous setbacks, and its difficulties and complexity have far exceeded CITIC Pacific’s expectations. The project’s commissioning date has been repeatedly postponed, and the project costs have been steadily rising. As of February 2013, CITIC Pacific had invested 9.1 billion U.S. dollars in the Western Australia iron ore project, yet some of the project’s construction work remained unfinished. At the end of 2013, the first batch of refined iron ore concentrate produced by the Western Australia project was finally shipped to China—four years later than the originally scheduled timeline. Meanwhile, starting in 2012... Iron ore prices continue to decline. Entering a downward trend, This could put the project in a situation where it starts incurring losses as soon as it begins production. In addition, CITIC Pacific and Clive Palmer, the actual controller of the original seller, Mineralogy, are... Ongoing disputes The two sides have filed lawsuits against each other several times, and there are still pending lawsuits to this day.
2006 In April, CITIC Pacific signed an agreement with Mineralogy to acquire all equity interests in Sino-Iron and Balmoral Iron.
2007 In January, CITIC Pacific Limited’s wholly-owned subsidiary registered in Australia. SinoIron With China Metallurgical Science and Industry Technology Corporation (hereinafter referred to as “MCC Group”) Signed for an amount of 11.06 The US$100 million Engineering, Procurement, and Construction (EPC) Contract for the Western Australia SINO Iron Ore Project (hereinafter referred to as the “EPC Contract”) The two parties will develop an iron ore mine in Australia, and the first shipment of iron ore is scheduled to be delivered in early 2009.
2007 In August, CITIC Pacific announced that it would sell a 20% stake in the Australian magnetite project to China Metallurgical Group. In addition, the two parties entered into a supplementary agreement to increase the contract price for the project’s engineering general contracting from USD 1.106 billion to USD 1.75 billion.
2007 In August, the project's commencement was forced to be postponed due to the failure to obtain approval for the environmental assessment and construction permit.
2008 In April, the project officially broke ground.
2008 In August, Rong Zhijian, Chairman of CITIC Pacific, stated that the capital expenditure for the Western Australia iron ore project in 2007 would be approximately US$3.5 billion, with the total project expected to require about US$3.8 billion. The project is forecast to produce roughly 27.6 million tons of iron ore sand by 2010.
2008 In October, CITIC Pacific announced that, in order to hedge against exchange rate risks associated with its Australian iron ore project, the group... Multiple cumulative leveraged foreign exchange trading contracts have been signed; however, due to the sharp decline in the Australian dollar, these contracts have already incurred realized losses of approximately HK$800 million. Based on the current exchange rate, the book loss by the end of this year will amount to as much as HK$14.7 billion.
2009 In March, CITIC Pacific announced that the Western Australia iron ore project, originally scheduled to begin production this year, is now expected to be delayed until the third or fourth quarter of 2010.
2011 In July, CITIC Pacific announced that the overall system commissioning of the Western Australia iron ore project would be delayed until the end of 2011. Consequently, the planned start of production and export of refined iron ore concentrate would also be postponed from the original schedule of late 2011 to the first half of 2012.
2012 In April, CITIC Pacific announced that it would exercise its subscription rights to acquire mining rights for an additional 1 billion tons of magnetite ore located in Western Australia, at a cost of US$200 million. Following the exercise of this first subscription right, the company will hold mining rights for a total of 3 billion tons of magnetite ore.
2012 In August, CITIC Pacific announced that the trial operation of the Western Australia iron ore project had been postponed from the end of this month to November.
2012 In November, Mineralogy, the seller of the Western Australia iron ore project, accused CITIC Pacific of breaching the contract and proposed unilaterally terminating the mining rights and mineral lease agreement.
2013 In February, Chang Zhenming, Chairman of CITIC Pacific, stated that CITIC Pacific has invested 9.1 billion U.S. dollars in the Western Australia iron ore project, of which 6.8 billion U.S. dollars was allocated to construction costs.
2013 In December, the first batch of refined iron ore concentrate produced by the Western Australia iron ore project was shipped to China.
2014 February of the year, CITIC Pacific’s application to the Australian court to block Clive Palmer’s operation of the port was dismissed. Clive Palmer It immediately filed an application with an Australian court, through its controlled company Mineralogy, to liquidate the China-Australia iron ore venture.